Financial and Physical Status of Works Report, Panchayati Raj XEN
Block-wise Status - SIRSA District
| S.No. | Block | Completed | In Progress | Not Started | Funds Not Received | Dispute | Not Feasible | MC Area | Tender in Process | Not Updated | Grand Total | Sanction Amount (₹ Cr) | Release Amount (₹ Cr) | Expenditure Amount (₹ Cr) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | BARAGUDHA | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 166 | 166 | 15.53 | 15.43 | 9.19 |
| 2 | DABWALI | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 241 | 242 | 41.32 | 40.77 | 27.55 |
| 3 | ELLENABAD | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 113 | 113 | 11.02 | 10.86 | 9.10 |
| 4 | NATHUSARI CHOPTA | 25 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 150 | 180 | 29.24 | 24.05 | 21.96 |
| 5 | ODHAN | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 175 | 175 | 21.77 | 21.41 | 14.95 |
| 6 | RANIA | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 148 | 148 | 20.18 | 19.97 | 15.68 |
| 7 | SIRSA | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 192 | 192 | 20.29 | 18.45 | 13.71 |
| GRAND TOTAL | 26 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 1,185 | 1,216 | 159.35 | 150.94 | 112.13 | |