Financial and Physical Status of Works Report, Panchayati Raj XEN

Block-wise Status - REWARI District

S.No. Block Completed In Progress Not Started Funds Not Received Dispute Not Feasible MC Area Tender in Process Not Updated Grand Total Sanction Amount (₹ Cr) Release Amount (₹ Cr) Expenditure Amount (₹ Cr)
1 BAWAL 8 55 2 0 0 0 0 0 184 249 26.80 20.60 17.48
2 DAHINA 9 27 2 0 0 0 0 0 59 97 12.48 9.32 9.68
3 DHARUHERA 11 1 2 0 0 0 0 0 132 146 16.34 15.96 10.13
4 JATUSANA 8 15 3 0 0 0 0 0 99 125 13.43 10.40 10.20
5 KHOL AT REWARI 6 17 4 0 0 0 0 0 79 106 13.26 10.97 10.15
6 NAHAR 2 4 4 0 0 0 0 0 114 124 13.70 13.04 9.14
7 REWARI 39 20 1 0 0 0 0 0 134 194 21.53 18.51 12.55
GRAND TOTAL 83 139 18 0 0 0 0 0 801 1,041 117.54 98.80 79.33