Financial and Physical Status of Works Report, Panchayati Raj XEN
Block-wise Status - BHIWANI District
| S.No. | Block | Completed | In Progress | Not Started | Funds Not Received | Dispute | Not Feasible | MC Area | Tender in Process | Not Updated | Grand Total | Sanction Amount (₹ Cr) | Release Amount (₹ Cr) | Expenditure Amount (₹ Cr) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | BADHRA | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2 | 2 | 0.24 | 0.24 | 0.24 |
| 2 | BAWANI KHERA | 65 | 49 | 3 | 0 | 2 | 1 | 0 | 0 | 0 | 120 | 13.48 | 12.45 | 10.14 |
| 3 | BEHAL | 12 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 53 | 66 | 19.46 | 19.46 | 19.46 |
| 4 | BHIWANI | 187 | 3 | 6 | 0 | 1 | 0 | 0 | 0 | 157 | 354 | 70.56 | 66.72 | 65.19 |
| 5 | DADRI-II | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 | 4 | 0.50 | 0.32 | 0.32 |
| 6 | KAIRU | 63 | 5 | 7 | 0 | 0 | 0 | 0 | 0 | 5 | 80 | 17.28 | 15.02 | 10.86 |
| 7 | LOHARU | 28 | 1 | 2 | 0 | 0 | 0 | 0 | 0 | 75 | 106 | 21.02 | 20.23 | 20.23 |
| 8 | SIWANI | 20 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 59 | 81 | 20.73 | 19.14 | 19.27 |
| 9 | TOSHAM | 39 | 4 | 8 | 0 | 0 | 0 | 0 | 0 | 107 | 158 | 29.83 | 26.71 | 25.87 |
| GRAND TOTAL | 415 | 63 | 28 | 0 | 3 | 1 | 0 | 0 | 461 | 971 | 193.10 | 180.28 | 171.58 | |